Oilsands Mines - Electricity and Natural Gas

2026

Purchased Electricity Generated Electricity Total Electricity Purchased Natural Gas
MWh MWh MWh 1000 m³
Aurora North & South (Syncrude Canada Ltd.)
January --- 136,155.9 136,155.9 69,983.3
February --- 111,503.9 111,503.9 58,001.5
March --- 113,130.9 113,130.9 53,423.1
April --- 128,943.9 128,943.9 58,916.0
May --- 123,893.6 123,893.6 56,828.1
June --- 116,911.5 116,911.5 51,281.1
Total --- 730,539.7 730,539.7 348,433.1

Base Mine (Suncor Energy Inc.)
January 224,115.0 744,970.0 969,085.0 272,182.1
February 196,078.0 660,873.0 856,951.0 238,371.3
March 200,769.0 744,510.0 945,279.0 267,988.3
April 130,751.0 795,734.0 926,485.0 260,675.6
May 6,482.0 760,854.8 767,336.8 236,408.5
June 82,068.0 696,075.0 778,143.0 224,952.5
Total 840,263.0 4,403,016.8 5,243,279.8 1,500,578.3

Fort Hills (Suncor Energy Inc.)
January 15.5 142,985.0 143,000.5 82,753.2
February --- 129,149.7 129,149.7 73,647.1
March 7,685.5 128,397.1 136,082.6 78,634.1
April 3,660.7 102,924.6 106,585.3 64,484.8
May 5,906.4 87,973.4 93,879.8 62,521.4
June 6.4 118,271.2 118,277.6 65,719.1
Total 17,274.5 709,701.0 726,975.5 427,759.7

Horizon (Canadian Natural Resources Limited)
January 56,941.9 149,456.2 206,398.1 157,772.7
February 47,132.3 137,893.7 185,026.0 148,918.4
March 49,678.7 152,207.2 201,885.9 148,168.2
April 73,081.5 123,311.9 196,393.4 147,925.5
May 607.0 134,796.1 135,403.1 153,295.7
June 62,227.0 127,551.8 189,778.8 151,652.5
Total 289,668.4 825,216.9 1,114,885.3 907,733.0

Jackpine (Athabasca Oil Sands Project)
January 40,607.5 --- 40,607.5 45,007.7
February 31,194.6 --- 31,194.6 41,298.4
March 31,519.8 --- 31,519.8 45,739.8
April 38,179.7 --- 38,179.7 45,623.3
May 34,492.3 --- 34,492.3 47,970.1
June 38,614.5 --- 38,614.5 40,281.3
Total 214,608.4 --- 214,608.4 265,920.6

Kearl (Imperial Oil Limited)
January 94,680.3 53,670.9 148,351.2 106,387.5
February 90,174.6 45,715.2 135,889.8 94,204.1
March 109,463.5 30,781.3 140,244.8 96,062.3
April 85,476.7 52,374.5 137,851.2 99,035.1
May 87,256.3 19,806.9 107,063.2 66,876.2
June 126,754.2 303.0 127,057.2 79,317.8
Total 593,805.6 202,651.8 796,457.4 541,883.0

Long Lake (CNOOC Limited)
January 7,429.0 --- 7,429.0 8,555.3
February 6,730.0 --- 6,730.0 7,620.6
March 7,518.0 --- 7,518.0 8,466.7
April 6,234.0 --- 6,234.0 7,960.9
May 6,110.0 --- 6,110.0 7,628.3
June 4,530.0 --- 4,530.0 5,615.6
Total 38,551.0 --- 38,551.0 45,847.4

Mildred Lake (Syncrude Canada Ltd.)
January 73,765.2 162,347.3 236,112.5 146,680.0
February 68,957.9 122,960.3 191,918.2 120,288.2
March 74,723.5 157,488.8 232,212.3 149,586.1
April 78,951.4 173,778.3 252,729.7 141,026.2
May 71,687.3 173,590.7 245,278.0 145,375.6
June 71,248.3 144,910.3 216,158.6 137,449.0
Total 439,333.6 935,075.7 1,374,409.3 840,405.1

Muskeg River (Athabasca Oil Sands Project)
January 488.7 140,391.8 140,880.5 110,614.5
February 1,731.1 124,228.3 125,959.4 100,508.7
March 6,485.9 133,694.8 140,180.7 109,855.5
April 2,950.6 129,105.0 132,055.6 108,577.2
May 42,239.7 84,129.6 126,369.3 90,384.7
June 33,318.8 87,429.8 120,748.6 85,139.1
Total 87,214.8 698,979.3 786,194.1 605,079.7

Redwater Upgrader (North West Upgrading Inc.)
January 92,085.5 --- 92,085.5 15,199.1
February 84,870.6 --- 84,870.6 13,974.5
March 93,404.6 --- 93,404.6 14,942.1
April 89,500.3 --- 89,500.3 14,286.6
May 90,342.4 --- 90,342.4 13,150.0
June 86,888.3 --- 86,888.3 11,813.7
Total 537,091.7 --- 537,091.7 83,366.0

Scotford Upgrader (Athabasca Oil Sands Project)
January 52,863.6 99,653.9 152,517.5 92,035.5
February 47,160.5 99,419.2 146,579.7 88,143.0
March 49,809.3 111,099.4 160,908.7 99,763.8
April 49,039.3 96,575.7 145,615.0 118,055.5
May 49,870.3 100,474.3 150,344.6 110,017.1
June 48,698.5 95,212.5 143,911.0 94,250.0
Total 297,441.5 602,435.0 899,876.5 602,264.9

Source: AER(Alberta Energy Regulator)