Menu

Oil Sands Mined Bitumen

2024

(tonnes)

Mined Grade Processed Grade
Aurora North & South (Syncrude Canada Ltd.)
January 8,041,639 11.21 % 7,784,825 11.21 %
February 9,322,855 11.28 % 9,121,745 11.30 %
March 10,411,024 11.75 % 10,580,968 11.79 %
Total 27,775,518 27,487,538

Base Mine (Suncor Energy Inc.)
January 13,413,950 10.20 % 14,037,999 9.80 %
February 13,904,342 10.00 % 14,538,562 9.50 %
March 14,833,183 11.00 % 15,325,895 10.60 %
Total 42,151,475 43,902,456

Fort Hills (Suncor Energy Inc.)
January 8,804,936 10.60 % 8,977,435 10.58 %
February 9,414,737 10.66 % 9,347,533 10.67 %
March 10,014,687 10.46 % 9,972,985 10.47 %
Total 28,234,360 28,297,953

Horizon (Canadian Natural Resources Limited)
January 16,199,804 10.10 % 15,959,439 9.69 %
February 13,617,876 9.89 % 141,027 9.57 %
Total 29,817,680 16,100,466

Jackpine (Athabasca Oil Sands Project)
January 7,082,585 11.90 % 6,973,810 11.70 %
February 5,540,856 11.70 % 5,402,448 11.70 %
March 6,024,308 11.70 % 6,116,940 11.60 %
Total 18,647,749 18,493,198

Kearl (Imperial Oil Limited)
January 13,056,804 11.29 % 13,115,225 11.30 %
February 12,991,904 11.31 % 13,250,087 11.35 %
March 14,412,494 11.55 % 14,687,680 11.57 %
Total 40,461,202 41,052,992

Mildred Lake (Syncrude Canada Ltd.)
January 9,633,946 10.88 % 9,633,946 10.88 %
February 8,136,185 10.39 % 8,136,186 10.39 %
March 8,812,208 10.53 % 8,419,233 10.48 %
Total 26,582,339 26,189,365

Muskeg River (Athabasca Oil Sands Project)
January 7,535,727 11.20 % 7,357,523 11.00 %
February 9,166,737 10.70 % 9,182,564 10.70 %
March 6,533,623 11.80 % 6,447,177 11.70 %
Total 23,236,087 22,987,264

Source: AER(Alberta Energy Regulator)